MSET – $44.4 Million paid out without formal lease agreements

Share This:

Auditor General's Findings

According to the Auditor General Report for FY 2018/19 [Section 3.2.160], contrary to Section 53 of the Financial Administration and Audit Act Regulation 2011, the Ministry of Energy, Science and Technology (MSET) did not have formal lease agreements for rental of office space at four locations for the operation of the Government Electrical Inspectorate (GEI) Division.

The report indicated that the Ministry made monthly payments over the period 2013/2014 – October 2019, totalling $44.4 million. In the absence of formal contracts, the rights and obligations of the parties might be misunderstood.

Responsive image

Permanent Secretary (current): Carol Palmer

Breach Category: Resource Management

Permanent Secretary (at breach): Hillary Alexander

Breach Type: Payments Without Supporting Contracts

Subscribe
Notify of
guest

0 Comments
oldest
newest most voted
Inline Feedbacks
View all comments

Most Recent Breaches

DCS – Unidentified lodgments totalling $2.1 million

April 18, 2023 | No comments

View Breach »

Accountant General – Pension Payments Made Without Verifying Life Certificates

April 18, 2023 | No comments

View Breach »

Accountant General – Overpaid Dependents a total of $4.1 million

April 17, 2023 | No comments

View Breach »

ACCOUNTANT GENERAL – Uncleared bank reconciliation items totalling $138.85 million

April 17, 2023 | No comments

View Breach »

MLSS – PATH protracted delay in upgrading the Beneficiary Management Info System

April 17, 2023 | No comments

View Breach »
0
Would love your thoughts, please comment.x
()
x

This site uses cookies to give you the best online experience. By using our site you agree to accept these cookies. Read more about it here.